Vinpac International and Cold Logic

Vinpac International

  • 2019-09-20

The Challenge: Vinpac International wanted to lift its capacity at its bottling and packaging site at Angaston in the Barossa Valley.  This included 60 new tanks and approximately 11ML of required tank cooling.  A combination of secondary ferment, cold stabalisation and  standard  holding temperature  conditions were simultaneously needing consideration. The Outcome: Cold Logic successfully installed […]

Continue reading
Teys Australia and Cold Logic

TEYS Australia

  • 2019-09-20

The Challenge: Upgrade the refrigeration plant to provide additional capacity and redundancy for the beef  carcass chillers. This project had to completed in a tight time frame all around live operation with no downtime to processing. This project included 2 additional screw compressor packages, new accumulator, electrical upgrade, new evaporative condenser and NH3 receiver. This […]

Continue reading

Rand Refrigeration Logistics

  • 2019-05-21

The Challenge:  Rand  Refrigerated Logistics expands its operations and sough to establish a new distribution centre in Parkinson, Queensland for both short and long term cold storage. The Outcome: Cold Logic  provided a full design and construct solution for both chilled and freezer rooms operating between -25°C and +2°C on ammonia refrigerant. This project was […]

Continue reading

Woolworths

  • 2019-05-21

Gepps Cross, Adelaide (SA) This project involves the supply and installation of temperature control and refrigeration services for the expansion of the original Woolworths distribution facility at Gepps Cross in Adelaide. The expansion added an additional 14,000 square metres of refrigerated and humidity controlled space. Larapinta, Brisbane (Qld) This project involves the supply and installation […]

Continue reading

Port Lincoln Tuna Processors

  • 2019-05-20

Long term trust in Cold Logic Port Lincoln Tuna Processors have entrusted their refrigeration design, installation and service to Cold Logic for over 25 years. Through their years of growth, Cold Logic has been an integral part of their operation. Port Lincoln Tuna Processors recent approached Cold Logic about additional capacity requirements and upgrade to […]

Continue reading

Yakult

  • 2019-05-20

The Challenge: Installation of a new ice tank along with 3 chilled water pumps and a chilled water buffer tank in order to increase the capacity of the chilled water. To other challenge was to use the existing refrigeration plant to supply the new upgraded ice bank and increase pump capacities on site. The Outcome:  […]

Continue reading

Thomas Foods International

  • 2019-05-20

Challenge: Thomas Foods (formally T&R Pastoral),  operated a processing facility in Murray Bridge, SA which was expanding to meet production demands. This presented significant problems, particularly in that upgrades  needed to be made while keeping the operation and refrigeration running. Outcome: Cold Logic worked extremely hard for many years to provide the latest refrigeration technologies […]

Continue reading